|
Flood Control After decades of governmental studies, on-again/off-again funding, several design changes and lots of public discussion, the $242 million Downtown Guadalupe River Flood Protection project was completed in 2004 – under the direction of the U.S. Army Corps of Engineers and the Santa Clara Valley Water District. The Downtown Project, which also incorporates park elements and trails developed by the San Jose Redevelopment Agency and the City of San Jose, stretches from Highway 880 south to Highway 280. The Santa Clara Valley Water District has two additional projects along the Upper and Lower Guadalupe that also integrate flood protection, public access and environmental restoration along the Guadalupe River from Almaden Valley to Alviso. The Lower Guadalupe project in the Alviso area was also completed in December 2004, ensuring that floodwaters from the upper reaches of the river can be carried successfully through the lower Guadalupe River to San Francisco Bay. The Upper Guadalupe project is scheduled to be constructed over the next 15 years. Together these projects will safeguard hundreds of homes, schools and businesses from flooding and also enhance habitat for endangered fish. Although the projects are being funded and constructed separately, the Water District is working together with cities and regulatory agencies to develop the projects utilizing a watershed-based approach. Park
Signage Frequently Asked QuestionsWhy did we need the project?The Guadalupe River frequently flooded San Jose's downtown and Alviso community, with numerous severe flooding events in its history. Most recently, the river flooded in 1982, 1983, 1986 and 1995. In February 1986, the river overflowed its east bank upstream of St. John Street, flooding residences and businesses. In January 1995, a similar flood occurred and flooded the same area. In March 1995, severe flooding occurred when the Guadalupe River and Los Gatos Creek combined to produce the highest flow in 50 years. In the most extensive flooding of the city's core in four decades, streets turned into rivers, forcing residents from their homes and driving office workers from high-rise buildings. Approximately 300 homes and businesses were flooded by four separate breakouts along the river, with damage estimates of up to $10 million. According to a 2001 U.S. Army Corps of Engineers report, average annual equivalent damages are $27.25 million. How does it work? The Lower Guadalupe Project improves the capacity of the river from the Bay to Highway 880, and was completed in December 2004. Now the channel is able to safely pass the 100-year flood flow from the Downtown Project. Similarly, with the Downtown Project complete, successfully handles the flows from the Upper Guadalupe Project, which will modify the channel from Highway 280 to Blossom Hill Road and is now in the engineering and design stages. With the proper permits and with funding from the federal government, the projected completion date for the Upper Guadalupe Project is December 2016. Why did the project take so long? The process to plan, design and build any project of this size and complexity is, by definition, a long one. The Guadalupe River plays many critical roles, as a habitat for fish, animals and plants; as a community resource; and as the main waterway to drain more than 170 square miles of Santa Clara County. Consequently, many regulatory and resource management agencies, municipal offices and community groups are interested and have had a voice in planning the project. That valuable input-gathering process is time-consuming. When was construction started? When was it finished? Construction actually began on the Downtown Project in 1992, and the section from Coleman Avenue to Highway 880 was completed in 1996. Between 1996 and 1999, construction was halted as the Guadalupe River Flood Control Project while the Collaborative worked to resolve concerns with the authorized project. The Corps of Engineers and the Santa Clara Valley Water District agreed to redesign some elements of the project in order to protect and preserve and/or restore the natural environment of the river, as well as provide flood protection. Those issues resolved. Construction began in October 1999 from Interstate 280 to Woz Way, near the Children's Discovery Museum. The remaining construction work on the project began in Spring 2002 and was completed in December 2004. What will happen to the fish? Throughout the county, the water district is working to protect and, in some areas, enhance the natural habitat in order to support the needs of native fisheries by removing barriers, installing fish ladders, and installing and maintaining shaded riverine aquatic cover to reduce water temperature and provide cover.
Will there be trails when the project
is finished? Will I no longer have to pay for flood
insurance? Can I eat the fish in the Guadalupe
River? Flooding History The Guadalupe River's natural channel directly upstream of the confluence with Los Gatos Creek has a capacity of 7,000 cubic feet per second (cfs), roughly the flow of a 10-percent or 10-year flood event. In February 1986, the river overflowed its east bank upstream of St. John Street, flooding residences and businesses. In January 1995, a similar flood occurred and flooded the same area. In March 1995, severe flooding occurred when the Guadalupe River and Los Gatos Creek combined to produce the highest flow in 50 years. In the most extensive flooding of the city's core in four decades, streets turned into rivers, forcing residents from their homes and driving office workers from high-rise buildings. Approximately 300 homes and businesses were flooded by four separate breakouts along the river, with damage estimates of up to $10 million. According to current U.S. Army Corps of Engineers estimates, average annual equivalent damages are $27.25 million. Project History Guadalupe River Flood Control Project Collaborative
The collaborative process was formalized with the creation of the Guadalupe River Flood Control Project Collaborative, a team of policy-level managers from the U.S. Fish and Wildlife Service, the State of California Water Resources Control Board, the National Marine Fisheries Service, the Natural Heritage Institute representing several environmental organizations, the California Department of Fish and Game, the San Francisco Bay Regional Water Quality Control Board, the Corps' Sacramento District, the City of San Jose, the San Jose Redevelopment Agency and the Santa Clara Valley Water District. The Collaborative set the following objectives to achieving a successful, long-term resolution to the issues mentioned above:
In July 1998, the Corps and District agreed to redesign a portion of the project and to revise the mitigation plan. Accordingly, the members of the Collaborative executed a Dispute Resolution Memorandum. The Corps and the District, in coordination with environmental regulatory agencies and the Collaborative, then refined the project modifications to satisfy the Endangered Species and Clean Water acts, and developed an acceptable mitigation and monitoring plan. The redesigned project and associated plans were offered for public input at scoping meetings in 1999, and the General Re-evaluation and Environmental Report, including the Environmental Impact Report and Supplemental Environmental Impact Statement, was approved by the Corps headquarters in 2001. On Nov. 16, 2001, the Army's Director of Civil Works signed the Record of Decision approving the modified project. Physical and Habitat Benefits
Economic benefits
Home |
The Park |
Maps/Directions |
History |
Events |
Education |
Calendar |
On-Line Store |